A | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 — Generate the material requirements You need BOM for each three products and — After completing plan develop load profile work center

PhysicsGeneralWorked Solution

(a) Generate the material requirements. You need a BOM for each of the three products (A, B, and C), beginning inventory levels, and scheduled receipts. The BOMs are shown in Figure. All items use lot-for-lot as the lot size rule. No beginning inventories exist. Lead time is two weeks for all items except items D and F, which have a lead time of three weeks. All other information is provided for you in Table.

.:.

(b) After completing the material requirements plan, develop a load profile for each work center for each week of the second quarter. Use the planned order releases and calculate the workload at each work center for weeks 14 through 26. The standard times are shown in the table. Use the load profiles to identify potential problems. The effective capacity at each work center is 960 hours each period.

.:.

The Newmarket International Manufacturing Company (NIMCO) was started by Marcia Blakely just two years after she finished graduate school. Her knowledge of mass customization has been the driving force behind NIMCO. The company produces three major custom products. Volume on the products is high even though each item is customized specifically for the customer. The products are processed through up to four different work centers. Even though each item is unique, the processing time at each work center is constant due to the sophisticated equipment used.

SOLUTION:

a.

A1213141516171819
Gross requirements760087009000
Scheduled Receipts
Projected Available 000000000
Planned order releases7600870090008700
A2021222324252627
Gross requirements8700800068003000
Scheduled Receipts
Projected Available 000000000
Planned order releases800068003000
D (L4L, LT = 3)910111213141516
Gross requirements228002610027000
Scheduled Receipts22800
Projected Available 000000000
Planned order releases261002700026100
D (L4L, LT = 3)1718192021222324
Gross requirements261000024000204009000
Scheduled Receipts
Projected Available 000000000
Planned order releases24000204009000
F (L4L, LT = 3)910111213141516
Gross requirements760087009000
Scheduled Receipts7600
Projected Available 000000000
Planned order releases870090008700
F (L4L, LT = 3)1718192021222324
Gross requirements8700800068003000
Scheduled Receipts
Projected Available 000000000
Planned order releases800068003000
E (L4L, LT = 2)910111213141516
Gross requirements152001740018000
Scheduled Receipts15200
Projected Available 000000000
Planned order releases174001800017400
E (L4L, LT = 2)1718192021222324
Gross requirements1740016000136006000
Scheduled Receipts
Projected Available 000000000
Planned order releases16000136006000
I (L4L, LT = 2)910111213141516
Gross requirements348003600034800
Scheduled Receipts34800
Projected Available 000000000
Planned order releases360003480032000
I (L4L, LT = 2)1718192021222324
Gross requirements320002720012000
Scheduled Receipts
Projected Available 000000000
Planned order releases2720012000
🔒

Unlock the complete assignment

You are viewing the free preview. Purchase this assignment once to reveal the complete resource.

$9.99 USD

Secure checkout is completed by Stripe.